Here's an update on our renovation as of 15-December-2012 (Saturday). Renovation is in high gear now as we approach the last 2 weeks of reno.

Car Porch:
  • [Done] Down lights installed
  • [Done] Prayers wall erected and skim-coated
  • In Progress: Skirting around the car porch
  • In Progress: Painting works
  • Pending: Gate change & auto-gate installation
  • Pending: Gate post lamps installation
  • Pending: Plugs x 2 to conceal the wires (to display firecrackers ornaments during CNY)
Living, Dining and Dry Kitchen:
  • In Progress: TV feature wall for living room
  • In Progress: Dry kitchen installation
  • Pending: Granite installation for kitchen counter top
  • Pending: Sink installation
  • Pending: High gloss spray paint works for cabinets
  • Pending: Doors change and installation
  • Urgent: Plaster ceiling cracked, gotto ask the plaster ceiling guy to come and fix them
  • Urgent: Dimensions for the fridge area incorrect, to resize the cabinets accordingly
Wet Kitchen:
  • Pending: Tiles for walls, flooring and kitchen counter
  • Pending: Granite installation for counter top
  • Pending: Sink installation
  • Pending: Hood installation
  • Urgent: Relocate Unifi box a little for it to be within the kitchen cabinets
Lighting & Fans:
  • [Done] Down lights installed
  • Pending: Living and dining room T-5 cove lights concealed around the plaster ceilings
  • Pending: Feature lighting for dining room
  • Pending: Pendant light for breakfast bar & altar area
  • Pending: Fans and toilet lights

Master Bedroom
  • In progress: Wardrobe installation 
  • In progress: Headboard installation

Other pending items:
  • Grills
  • Paint works
  • Plaster ceiling touch ups
  • Air-cond installation
  • Electrical items to be purchases